7 Floors Tall!

October, 7 2020


It is with the changing of the season that we bring you the latest update from EuroCity. We’re delighted to report that second instalments for both the towers were received in full, an amazing achievement in the current climate! On the site, both Carrara and Murano have been progressing nicely, with the 7th and 5th floors in each respective tower now completed. The transfer slab for the final tower, Porcelana, is also under construction, and we can expect concrete to be poured in two weeks time. Meanwhile in the basement level works are becoming even more complex, with the first fixing of the fire-safety sprinkler system and drainage underway.

The structure of the development is really taking shape now, with an average of 3 floors being constructed per month – so if you happen to be passing the site you will really be able to see a big difference in the coming months. You can also catch up with all of these exciting developments via the latest instalment of our time-lapse video, featured below!